Ongoing Project In progress

Caculo Cabaça Hydropower Plant

Client
CGGC – Energy China
Location
Cuanza Norte, Angola
Status
In progress

Description

Caculo Cabaça Hydropower Plant in Angola, with 2,172 MW of installed capacity (4 × 543 MW).

Main scope
• Professional technical consulting services for electrical, mechanical and civil works integration and interfaces
• Team of specialists: mechanical engineer, electrical engineer and civil engineer

Additional information

End client: GAMEK
Contract term: December 2025 to December 2026
Current workforce: 3 specialists
Physical progress: 15% (July 2026)